Contract Matters

Clear by Design

Court confirms that express contract terms prevail when interpreting parties’ design responsibilities. Design and build projects proceed on the basis that the contractor bears responsibility for carrying out and completing...

No Second Chance

Court of Appeal upholds contractor’s right to terminate JCT contract for repeated late payment by employer. The Court of Appeal has issued a significant decision regarding the interpretation of clause...

One Decision at a Time, Please!

Court declines to set-off second adjudicator’s award.   Frustrated respondents should be aware that a request to set-off a second adjudication decision between the same parties in defence of a...

Collateral Warranty v Construction Contract

U.K. Supreme Court confirms that a collateral warranty is not a construction contract. In Abbey Healthcare (Mill Hill) Ltd. (“Abbey”) v Augusta 2008 LLP (formerly Simply Construct (UK) LLP) (“Simply”)...

Intent on Disaster

The perils of relying on a letter of intent In CLS Civil Engineering Ltd. v WJG Evans and Sons [2024], the court found that in the absence of a formally...

Pay First or Risk Disappointment

Court declines to save “true value” adjudication commenced prematurely. In Henry Construction Projects Ltd. v Alu-Fix (UK) Ltd. [2023], the Technology and Construction Court (TCC) dismissed a contractor’s application for...

Works Despite Quirks

Liability cap upheld by TCC notwithstanding difficult language In Drax Energy Solutions Ltd. v Wipro Ltd. [2023], the Technology & Construction Court (“TCC”) upheld a contractual clause said to impose...

Fractions in a Day

How do the courts interpret a “day” under a construction contract?  In Elements (Europe) Ltd v. FK Building Ltd. [2023], the Technology & Construction Court (“TCC”) has provided helpful guidance...

The Risks of Contracting With a Dormant Company

The case presented shows the importance of checking the identity and status of proposed parties when agreeing to a contract. In WRB (NI) Ltd. Henry Construction Projects Ltd. [2023], the...

Be Specific!

Validity and interpretation of pay less notices In the case of Advance JV & Ors -v- Enisca Ltd. [2022] EWHC 1152, the Technology and Construction Court (TCC) considered the validity...

elevator_world_inc__logo

EW U.S. Office Closed for Fourth of July

Vasa

TKE Names Vasa Chief People Officer

Feenstra

Wittur Appoints Feenstra as CCO, President and GM EMEA

EFESME’S BOD AND GENERAL ASSEMBLY REVIEWS FUTURE OF EUROPEAN LIFT SMES

EFESME’s BoD and General Assembly Reviews Future of European Lift SMEs

Dr. Peter Lauer; image courtesy of VFA-Interlift

In Memoriam: Dr. Peter Lauer