Contract Interpretation and Repudiatory Breach

Contract-Interpretation-and-Repudiatory-Breach

In the recent case of Optimus Build Ltd. v. Southall & McManus, the Technology and Construction Court (TCC) considered a dispute in which the contractor believed the contract was a fixed-price contract, and the employer believed it to be a cost-plus contract. Both parties claimed the other committed a repudiatory breach before the works had been completed, but who really committed the repudiatory breach?

Background

In March 2017, Mr. Southall and Ms. McManus (the “Employers”) purchased a property in Worsley, Manchester, and engaged Optimus Build Ltd. (the “Contractor”) to undertake wide-ranging improvements, including a three-storey extension and structural alterations.

The contract between the Employers and the Contractor was formed during the course of a series of meetings and documentary exchanges. The documents included various versions of what was described as a budget estimate, as well as numerous emails. The works progressed until the third valuation, at which point a dispute arose.

What was the claim?

The Contractor commenced proceedings claiming the Employers had wrongfully repudiated the contract and the Contractor was entitled to the balance of the fixed-contract price for the works undertaken, plus loss of profit on the remaining works.

The Employers argued the contract was a cost-plus contract, and the Contractor had wrongfully repudiated the contract, meaning the Contractor’s claim for the balance was made on the wrong contractual basis, was overstated and the Contractor was not entitled to claim for loss of profit. The Employers claimed an entitlement to delay-related losses arising from the repudiation.

What type of contract was it?

The judge noted the Employers lacked experience and knowledge of the construction industry, and, therefore, he was prepared to accept they might mistakenly have believed the contract was cost-plus, in part, because the pricing document was headed “budget estimate.”

However, the judge considered the Contractor would not have produced a budget estimate if cost-plus had clearly been agreed. Furthermore, on the Employers’ version of events, they ought to have noticed and queried that the budget estimate did not specify the Contractor’s percentage addition for profit. As a result, the judge concluded the contract was on a fixed-price basis.

Where it all went wrong

The trigger for the dispute was the submission of the third interim valuation submitted on 26 September 2018. Mr. Southall responded asking for a breakdown of each individual item, and the parties attended a site meeting to discuss matters. The site meeting became contentious, and Mr. Southall stated the Contractor should not carry out any further work until they provided an itemised breakdown of the next month’s work.

Repudiatory Breach

On 5 October 2018, the Contractor sent an email, which, amongst other things, stated the Contractor believed the best approach was for three things to occur:

  • valuation three to be paid in full;
  • the full scope of the Contractor’s remaining works to be established and
  • a mutually acceptable payment plan be put in place to cover the remaining works.

At the end of this email, the Contractor suggested arranging a meeting to try to agree on a way forward, and stated, “Until we feel comfortable with the situation, we will not be carrying out any further works.”

The Employers argued this email amounted to a repudiatory breach of contract because the Contractor had no contractual right to suspend the works for non-payment or otherwise. Further, the Employers said the Contractor’s demand for immediate payment of the third valuation in full whilst there remained a genuine dispute as to its amount and for an agreed-upon payment plan were both unjustified from a contractual perspective.

The Contractor submitted the email was not repudiatory because, even though the Contractor did not have a contractual right to suspend the works, the concerns they raised were justified in the context, and unless matters were resolved, they could not proceed with the works anyway (given the uncertainty as to what works they were required to undertake).

The judge found the Employers were not entitled to treat the email as repudiatory. The Contractor were not saying they would not carry out any further work until the three points in the email were agreed; rather, they were asking for a meeting to resolve those issues. The judge also stated there was no basis for the Employers to conclude the offer of a meeting was entirely empty, and so they should not have treated the email as repudiatory.

However, the Employers had treated the email as a repudiatory breach and proceeded to have the remaining works costed by other contractors. They had explained to the Contractor that they planned to appoint an independent quantity surveyor to inspect the works, and they would subsequently contact the Contractor for a meeting. The judge considered this a clear communication of acceptance of the Contractor’s alleged repudiation.

On 12 October 2018, after the Employers refused to meet the Contractor to resolve the matter, the Contractor emailed the Employers stating that by refusing to meet and insisting the Contractor remove their equipment from site and not return, the Employers were in repudiatory breach, and that this was accepted by the Contractor.

The judge held the Employers were in repudiatory breach of contract, and awarded the Contractor the amount of £23,628.36 for work done and £19,422.96 for damages for breach of contract.

Analysis

This decision is a stark reminder that wrongful acceptance of a purported repudiatory breach can itself be a repudiatory breach of contract with costly implications. It also highlights the important point that a wrongful suspension of performance does not, in itself, necessarily amount to a repudiatory breach that would justify the other party as treating itself as discharged from any further obligation to perform its obligations under the contract.

This article contains information of general interest about current legal issues but does not provide legal advice. It is prepared for the general information of our clients and other interested parties. This article should not be relied upon in any specific situation without appropriate legal advice. If you require legal advice on any of the issues raised in this article, please contact one of our specialist construction lawyers. © Hawkswell Kilvington Limited 2021

Since 1953, Elevator World, Inc. has been the premier publisher for the global vertical transportation industry. It employs specialists in Mobile, Alabama, and has technical and news correspondents around the world.

Get more of Elevator World. Sign up for our free e-newsletter.

Please enter a valid email address.
Something went wrong. Please check your entries and try again.
Building-R-Waygood-and-Otis-Elevator-Co-in-the-UK

Building R. Waygood and Otis Elevator Co. in the U.K.

IoT: Magic or Myth?

IoT: Magic or Myth?

Astro-Dog-Apollo-Lifts-Off-for-First-Ever-Space-Walkies

Astro-Dog Apollo ‘Lifts Off’ for First-Ever Space Walkies

Model-Lifts

Model Lifts

Technology-Ahead

Technology Ahead

NOVA Elevators Introduces Vocal Suite

NOVA Elevators Introduces Vocal Suite

Is-Your-Lift-Safety-Compliant

Is Your Lift Safety-Compliant?

Remote Monitoring: Risks and Rewards

Remote Monitoring: Risks and Rewards