Pay First or Risk Disappointment

Pay First or Risk Disappointment
image adobe stock

Court declines to save “true value” adjudication commenced prematurely.

In Henry Construction Projects Ltd. v Alu-Fix (UK) Ltd. [2023], the Technology and Construction Court (TCC) dismissed a contractor’s application for summary judgment to enforce a “true value” adjudication decision in its favour as that adjudication had been commenced before the contractor had discharged its immediate payment obligation to its subcontractor arising from an earlier dispute.

This was notwithstanding the earlier award had, in the meantime, been paid.

Background

In June 2021, Henry Construction Projects Ltd. (“Henry”) engaged Alu-Fix (UK) Ltd. (“Alu-Fix”) under a JCT (Joint Contracts Tribunal) standard building sub-contract, to carry out works at a boutique hotel development in central London (the “Sub-Contract”).

Following a dispute, on 11 November 2022, Alu-Fix terminated the Sub-Contract at will pursuant to clause 7.12. This triggered the payment mechanism contained in clause 7.11, which required Alu-Fix to submit an application for payment. Alu-Fix submitted that application on 15 November 2022 in the sum of c.£260k plus VAT, and Henry had until 13 December 2022 to pay the notified sum.

The Adjudications

On 15 December 2022, following Henry’s failure to pay, Alu-Fix referred the matter to adjudication on what is commonly referred to in the construction industry as the “smash and grab” basis — that is to say that Henry had failed to give notice of its intention to pay less than the notified sum.

In response, Henry contended it had submitted two potentially valid pay less notices on 25 November and 12 December 2022, respectively.

On 18 January 2023, before any decision had been reached in the “smash and grab” adjudication, Henry commenced its own “true value” adjudication claiming that Alu-Fix was, as a result of overpayment, indebted to Henry in the sum of c.£235k plus VAT.

On 23 January 2023, Alu-Fix wrote to the “true value” adjudicator, Mr. Molloy, challenging his jurisdiction and requesting that he resign. Mr. Molloy declined to resign.

By a decision dated 27 January 2023, the “smash and grab” adjudicator, Mr. Rayner, instructed Henry to pay Alu-Fix the sum of c.£260k by 3 February 2023 (the “Rayner Decision”). Mr. Molloy stayed the “true value” adjudication pending payment by Henry of the Rayner Decision; and confirmed he would resign if payment was not made in accordance with that Decision. On 2 February 2023, Henry made full payment to Alu-Fix in accordance with the Rayner Decision and the stay of the “true value” adjudication was lifted.

The Dispute

By a decision dated 6 March 2023, in respect of the “true value” adjudication, Mr. Molloy found that Alu-Fix was indebted to Henry in the sum of £190k plus interest (the “Molloy Decision”).

Alu-Fix failed to comply with the Molloy Decision and argued that Mr. Molloy had had no jurisdiction to reach his decision, as Henry had commenced the “true value” adjudication before making payment of the notified sum pursuant to s.111 of the Housing Grants, Construction and Regeneration Act 1996 (the “Act”)

In response, Henry applied to the TCC for summary judgment, maintaining it should be allowed to rely upon the Molloy Decision, having made payment of the Rayner Decision, which had followed the raising by Henry of a “genuine dispute,” namely, contending the validity of the two pay less notices.

The key legal principles set out in Bexheat v Essex Services Group [2022] and relied on by the Judge in this case were as follows:

  • Where a valid application for payment has been made by a contractor in accordance with the terms of a construction contract falling within the scope of the Act, an employer who fails to issue a valid payment or pay less notice must pay the notified sum in accordance with s.111 of the Act by the final date for payment.
  • The courts will take a robust approach to adjudication enforcement, enforcing adjudicators’ decisions by summary judgment regardless of procedural errors, fact or law. The exceptions to this rule are where the adjudicator has acted without jurisdiction or has breached the rules of natural justice.
  • Where a party is required to pay a notified sum following its failure to issue a valid payment or pay less notice, such party is entitled to commence a true value adjudication in respect of that sum (but only if it has complied with s.111 of the Act).  

The Court’s Decision

The Judge, DJ Baldwin, refused Henry’s application for summary judgment to enforce the Molloy Decision.

In accordance with s.111(1) of the Act, the notified sum must be paid by the final date for payment, which creates an immediate payment obligation. The Rayner Decision determined the final date for payment by Henry was 13 December 2022 and that was the date the immediate payment obligation commenced. The Judge rejected Henry’s contention that the final date for payment was 3 February 2023 and described this date as the “final date for late payment.” As such, Henry had not been entitled to commence a “true value” adjudication on 18 January 2023, without having first discharged its immediate payment obligation pursuant to the Rayner Decision, and as a result Mr. Molloy lacked jurisdiction.

The court also made observations regarding Henry’s submission that there had been a “genuine dispute” as to any purported immediate payment obligation. The Judge considered that Henry’s argument as to the existence of a genuine dispute risked tipping the balance unfairly towards the disputing party and essentially prejudiced the right of the payee to be paid, which would ultimately undermine the cashflow policy of the Act. To find otherwise would amount to asking the court to launch a value judgement as to whether any rejected dispute raised was “genuine” or not.

The Judge did add that if the Rayner Decision had upheld a “zero” pay less notice, or the validity of Alu-Fix’s underlying application had been successfully challenged, then there would, in his view, have been no notified sum within the meaning of the Act and therefore no immediate payment obligation. In those circumstances, the “true value” adjudication “may well not, on the facts, be found to be premature and reliance on it might well be permitted.”

Analysis

This case lends further support to the court’s policy of “pay now, argue later.” Although it does not fully close the door on commencing a true value adjudication prior to the outcome of a “smash and grab” adjudication and later relying on the “true value” adjudication, it ought to serve as a further deterrent to those considering such a course of action, unless they have, in the words of the Judge, “a sufficient level of confidence that any dispute raised [in the ‘smash and grab’ adjudication] should result in a finding of no immediate payment obligation having been established.”

This article contains information of general interest about current legal issues but does not provide legal advice. It is prepared for the general information of our clients and other interested parties. This article should not be relied upon in any specific situation without appropriate legal advice. If you require legal advice on any of the issues raised in this article, please contact one of our specialist construction lawyers. © Hawkswell Kilvington Ltd. 2024

Thomas Salter focuses on contentious matters and advises on complex construction and engineering disputes throughout the contractual supply chain. Disputes frequently concern extensions of time, variations, non-payment and contract formation. Thomas has extensive experience of all standard forms of contract including JCT, NEC and FIDIC, and is frequently asked to provide contractual and commercial advice to clients during ongoing projects. Thomas is regularly instructed to represent clients in adjudication, litigation (usually in the Technology and Construction Court), arbitration and mediation.

Get more of Elevator World. Sign up for our free e-newsletter.

Please enter a valid email address.
Something went wrong. Please check your entries and try again.

Elevator-World---Fallback-Image

Safety Appliances for Lifts: 1895(Part 3)

IoT Takes the Elevator World Into Industry 5.0

IoT Takes the Elevator World Into Industry 5.0

ELEVATOR WORLD’S 26th Annual Project of the Year

ELEVATOR WORLD’S 26th Annual Project of the Year

CASA Boutique Hotel

CASA Boutique Hotel

Elevator-World---Fallback-Image

The Good, the Bad, the Strange

Elevator-World---Fallback-Image

Pickerings Go From Strength to Strength

Digitalisation’s Impact

Digitalisation’s Impact

Accelerating Decarbonization

Accelerating Decarbonization