No Time To Lose!

No Time To Lose!
Photo: Adobe Stock

The implied obligation as to time for completion and the perils of failing to progress works expeditiously

In the recent case of Barkby Real Estate Developments Ltd. v. Cornerstone Telecommunications Infrastructure Ltd. [2022] the Technology and Construction Court (TCC) held a contractor liable to its employer for failing to complete its works within a “reasonable time,” pursuant to section 14 of the Supply of Goods and Services Act 1982.

Background 

The Claimant (“BREDL”) engaged the Defendant (“Cornerstone”) to assist with the removal, replacement and relocation of a mobile telephone mast at a development at Bexhill Road, Hastings (the “Development”). No formal written contract was entered into between the parties.

The purpose of moving the existing mast was to improve the sight line of vehicles leaving the Development, which would otherwise be obstructed.

Cornerstone finalised its original foundation design for the mast relocation at end of March 2019, but a re-design was required as a result of inadequate ground conditions discovered only after works had commenced on site.

The ground conditions issue resulted in a delay to completion of Cornerstone’s works of some five months. Cornerstone eventually completed its works on 7 August 2020 and practical completion of the Development took place on the same date.

Crucially, BREDL claimed that, but for Cornerstone’s delay in completing its works, the completed Development would have been handed over to its purchaser, Hastings Borough Council, no later than 30 June 2020. BREDL sought recovery of finance costs and other losses said to have resulted from the delay in handover of the Development.

Court’s Decision

Cornerstone was responsible for the five-month delay to completion of its works, and this, in turn, had impacted critically upon the date for handover of the Development. BREDL was awarded most of its additional project finance costs and all of its additional management costs, which were not too remote.

What Were the Terms of Cornerstone’s Contract With BREDL?

Although there was no formal written contract between the parties, the Court nevertheless found that a binding agreement existed and had been formed on 5 September 2019 when Cornerstone acknowledged receipt of BREDL’s payment following its acceptance of a quote.

In the absence of any express terms as to the time for performance, the Court also found that there was to be implied into the contract, by operation of section 14 of the Supply of Goods and Services Act 1982, a term that the “supplier will carry out the service within a reasonable time.”

What Was a “Reasonable Time” for Completion of Cornerstone’s Works?

The Court analysed events that occurred during the build phase of the works and concluded that, but for the five-month delay, which was attributable to unsatisfactory ground conditions, Cornerstone would have completed its work by the end of March 2020 as initially envisaged, rather than on 7 August 2020.

As to responsibility for the ground conditions issue, the Court held that Cornerstone’s original design of the foundations was inadequate. Having heard expert opinion evidence, the Court agreed with BREDL that a competent designer would have arranged for a geotechnical survey to be carried out before finalising its design. Cornerstone did not do this and, as a result, it had to redesign the foundations which delayed the works.

In support of its finding that Cornerstone had failed to carry out its works within a reasonable time, the Court also drew on the following:

  • No explanation was given by Cornerstone as to why it took an additional five months to resolve the problems identified with its initial foundation design.
  • Other complications attributable to Cornerstone compounded the delays. Cornerstone ordered a replacement mast, for example, and then allowed this to be used on another site, which prevented the site from being connected to power. Cornerstone had also allowed a contract for the supply of fibre to lapse, which created further delay.
  • Cornerstone was busy with 50 different contracts on the go at the time of the contract in question and had failed to give appropriate priority to this project.

In short, the Court was satisfied Cornerstone had failed to complete its works within a reasonable time.

This case serves as a reminder to contractors that in the absence of a formal contract, they are still likely to be under an implied obligation to complete their works within a reasonable time.

Was BREDL Entitled to Damages, and, if So, in What Amount and Are These Too Remote?

The TCC was also satisfied that Cornerstone’s delay in completing its works meant that the sale of the Development was in turn delayed. Cornerstone had been made aware by BREDL that completion of its works was needed to enable BREDL to achieve its objectives and that the “build contract” (i.e., the main Development) programme was only scheduled to last eight months. The Court also wasted little time dismissing Cornerstone’s contention that the main works to the Development had themselves been incomplete, such that any delay attributable to Cornerstone’s works had not, in fact, occasioned BREDL any loss.

BREDL claimed the delayed sale of the Development meant it was unable to redeem a loan within the timeframe envisaged, which had resulted in it incurring additional fees and interest. BREDL also claimed to have incurred additional project management costs.

The Court found that BREDL was entitled to recover most of its additional financing costs and all of its additional management costs. These losses would not have been incurred had Cornerstone completed its works on time. (On the facts, BREDL’s claim for additional financing costs succeeded only in part because had practical completion been certified on time, it would still have taken approximately 21 days for the transaction to complete).

The Court rejected Cornerstone’s submission that these losses were too remote, holding that knowledge on the part of Cornerstone of the precise details of BREDL’s financial arrangements was not necessary. It was enough that there was a serious possibility that BREDL’s ability to pay off its financing was tied to practical completion and sale of the project.

Analysis

This case serves as a reminder to contractors that, in the absence of a formal contract, they are still likely to be under an implied obligation to complete their works within a reasonable time. The case also illustrates the importance of progressing works expeditiously, so as to meet the employer’s stated objectives. In this case, the Court was unable to reconcile the contractor’s expected total time on site of 11 working days with the five-month delay to completion of its works. Even once the problem with inadequate ground conditions had been identified, Cornerstone had not acted with reasonable expedition to resolve the issue, which ultimately proved to be its undoing.

This article contains information of general interest about current legal issues but does not provide legal advice. It is prepared for the general information of our clients and other interested parties. This article should not be relied upon in any specific situation without appropriate legal advice. If you require legal advice on any of the issues raised in this article, please contact one of our specialist construction lawyers. © Hawkswell Kilvington Ltd. 2022

Thomas Salter focuses on contentious matters and advises on complex construction and engineering disputes throughout the contractual supply chain. Disputes frequently concern extensions of time, variations, non-payment and contract formation. Thomas has extensive experience of all standard forms of contract including JCT, NEC and FIDIC, and is frequently asked to provide contractual and commercial advice to clients during ongoing projects. Thomas is regularly instructed to represent clients in adjudication, litigation (usually in the Technology and Construction Court), arbitration and mediation.

Get more of Elevator World. Sign up for our free e-newsletter.

Please enter a valid email address.
Something went wrong. Please check your entries and try again.

Elevator World UK | 4th Quarter 2022

LiftEx and LEEA Awards 2022

LiftEx and LEEA Awards 2022

Safety First

Safety First

SILC 2022

SILC 2022

Successful Events and Safety

Successful Events and Safety

The Largest UK Exhibition Ever Organized: Liftex 2022

LIFTEX 2022

EOX: Eco-Efficient and Natively Digital

EOX: Eco-Efficient and Natively Digital

IoT Safety Predictive Monitoring of Lift Operations, Shafts and Buildings

IoT Safety Predictive Monitoring of Lift Operations, Shafts and Buildings

Appraisals? Let’s Sack Them

Appraisals? Let’s Sack Them

Elevator World UK | 4th Quarter 2022